News

 

Field and CPL Updates

2006 Greenland

June 18, 2006
Update provided by Jay Johnson
project update image
Michael Jayred breaking a core barrel connection.

Activity: DISC Drill Test - Summit Greenland

Period: 6/12-6/17/06

Weather Conditions: Temperature range -28°C to -8°C, wind 2-19 knots.

ICDS Personnel on Site:
Jay Johnson
Kristina Dahnert
Michael Jayred
Bill Mason
Nicolai Mortensen
Paul Sendelbach
Laurent Augustin
John Robinson
Scott Hamon
John Fowler

Activities During Period:

Personnel - On Wednesday Laurent Augustin and John Robinson left camp and John Fowler came in. John will be working with us until the end of the season.

Drilling - This week we drilled a total of 175.933 meters. The borehole depth is 458.543 meters. The average core length was 2.19 meters. The longest core drilled this week was 3.08 meters. The average core length we are able to drill has decreased as we have drilled deeper. We have been running each drill run until we lose penetration. The screens are full when a three meter core is drilled, but when we lose penetration with shorter cores it is due to the head plugging only. The screens still have space in them for more chips. This week we have been experimenting with feeding the drill fast enough for the drill to ride on the shoes. When we do this the cable tension and motor current graphs smooth out. We have had the best luck drilling long cores by dropping about 1000n of tension off the crown sheave at the beginning of the drill run and holding that tension for the remainder of the run. We have been running the cutter between 60 and 90 rpm and the pump from 2000 to 3000 rpm during this week's tests. Feed rates have ranged from 5 to 10 mm/s. Running the drill on the shoes has greatly reduced the number of fractured cores.

Core dog cages - When the cutter head gets packed with chips the core dogs also get chips packed behind them so they can't retract when pushing the core out. To solve this problem I milled a notch in each core dog cage so any chips that get packed behind them can be cleaned out or will push out of the openings when the core is pushed out. This modification is working very well.

Instrument section - Due to the problems with getting the cutter motor to start, we switched from instrument section K to section J at the beginning of the week. Section J initially ran better, but then we began having problems getting the pump motor to start. This is the same problem we were having with the cutter motor and the K instrument section. Nicolai opened up the K instrument section. While he was looking for problems, the solder on the side of a connector on the cutter motor controller board fell off. All eight solder joints on the connector were bad. He fixed the connector and we put this instrument section back in service. It has been working without problems since the fix. Current drill configuration is "A" anti-torque section, "K" instrument section, and "Z" motor section.

Winch - The level wind on the winch continues to fault out now and then. We are typically tripping down hole at only 0.5 m/s to avoid having to restart a drill run due to the level wind faulting. The latest problem is that when you are in computer mode with the winch tripping down hole and you tell it to stop it can take up to 30 meters for the winch to stop. Sometimes it will stop in less, but not predictably. Paul changed the deceleration rate parameter in the computer and the winch stops better now, but the problem isn't truly fixed.